Pocatello Regional Airport - Rehabilitate Taxiway A North Terminal Apron and FBO Apron

Rehabilitate Taxiway A North, Terminal Apron, and FBO Apron Construct Concrete Hardstand, Upgrade Electrical Vault, Replace Rotating Beacon

Status

Bidding Closed

Prebid Date4/18/19 11:00 am

Bid Date5/1/19 2:00 pm

Company & Contacts

T-O Engineers

Jared Norton (jnorton@to-engineers.com)   208-323-2288

Location

Pocatello, Idaho

Work associated with proposed improvements is generally described as follows:

Schedule A

Rehabilitate Taxiway A North consists of mill and inlay a portion of parallel Taxiway A and widening Taxiway A2. Work includes asphalt pavement removal, excavation, subbase course, base course, asphalt mix pavement, drainage improvements, taxiway edge lights, guidance signs relocation, and pavement marking. Approximate quantities include 35,000 SY asphalt pavement milling, 3,000 CY excavation, 400 CY subbase course, 300 CY base course, 7,500 tons of asphalt mix pavement, 22 elevated edge lights, 1,400 LF electrical conduit, 2,000 LF lighting cable, 8,000 SY pavement seal coat, and 30,000 SF pavement marking.

Schedule B

Rehabilitate Terminal Apron consists of mill and inlay a portion of the terminal apron and construct concrete pavement. Work includes asphalt pavement removal, excavation, subbase course, base course, asphalt mix pavement, concrete pavement, seal coat, pavement marking, and other items. Approximate quantities include 38,000 SY asphalt pavement milling, 400 CY excavation, 50 CY subbase course, 150 CY base course, 7,500 tons of asphalt mix pavement, 600 SY of concrete pavement, and 7,000 SF pavement marking.

Schedule C

Rehabilitate FBO Apron consists of mill and inlay a portion of the FBO apron. Work includes asphalt pavement milling, asphalt mix pavement, pavement marking, and other items. Approximate quantities include 28,000 SY asphalt pavement milling, 7,000 tons of asphalt mix pavement, and 3,000 SF pavement marking.

Schedule D

Construct Concrete Hardstand consists of construction of a concrete pavement aircraft parking position. Work includes asphalt pavement removal, excavation, subbase course, base course, asphalt mix pavement, concrete pavement, and pavement marking. Approximate quantities include 1,500 SY asphalt pavement removal, 750 CY excavation, 50 CY subbase course, 250 CY base course, 1,200 SY of concrete pavement, and 1,000 SF pavement marking.

Schedule E

Upgrade Electrical Vault Equipment consists of replacing existing regulators and the pilot controlled lighting, and installing other miscellaneous electrical equipment in the existing vault building.

Schedule F

Replace Rotating Beacon consists of replacing the existing rotating beacon located on top of the Air Traffic Control Tower.