Schedule A: Northeast Apron Reconstruction work includes asphalt pavement removal, excavation, subbase course, base course, hot mix asphalt pavement, concrete pavement, pavement marking and other items. Approximate quantities include 16,000 SY of asphalt pavement removal (by rotomilling), 6,000 CY of excavation, 4,000 CY of subbase course, 2,600 CY of base course, 3,500 tons of hot mix asphalt pavement and 625 SY of concrete pavement.